Construction update: Second week of September
By Jeff Zeitler on Wednesday, September 13th, 2017
Since last post we have:
Finished patching and painting the front steps and landing
Taped and mudded all the taproom drywall
Drywalled the entire basement
Our plumbing and HVAC contractor have finished installing our new heating and cooling system, and plumbing is roughed in and inspected.
Electrical stuff is mostly roughed in at this point.
We discovered an old window that had been converted into a built-in shelving unit, then covered with sheetrock in the 1980s. We’re restoring it!
Concrete board behind the bar is installed and ready for tile.
And our sign is finally done!